11.30 BRIDGES
Reporting of vertical clearance changes is accomplished by placing information on "CARS 511" (Condition Acquisition & Reporting System). Refer to the CARS Users Manual for more information (http://dotnet/construct/CARS.doc).
11.31 FALSEWORK
NOTE:
1. No bolt without a weakened section may be used.
2. No hold-down device shot into the floor will be allowed.
Falsework Plans
Specification
Submitting Plans
The contractor should be informed at preconstruction conferences that falsework plans must be
submitted and reviewed prior to the erection of any falsework elements. The Office of Bridges &
Structures has revised their policy on falsework plan submittal and review to improve the efficiency
and timeliness of response. The process for falsework plan submittal is explained in the following:
Falsework plan submittals should include the following information: County, Project Number, Design Number, and Contractor. The contractor should submit the falsework plans directly to the Office of Bridges & Structures with a cover letter requesting review for approval. The contractor will also distribute copies of the cover letter from the plan submittal to the RCE and Office of Construction.
The Office of Bridges & Structures will review the falsework plan submittal and send the final approved copies to the contractor, RCE, and retain a copy in the bridge file. If the project is a consultant design, the Office of Bridges & Structures may have the consultant review the falsework plan in which case the consultant would also retain a final copy of the approved plans for their file. Resubmittal will be required when the original falsework plans are deemed inadequate.
Included with the distribution of the final approved falsework plans will be a cover letter. This cover letter will be copied to the
Special instructions for counties and cities are included in Appendix 11-22.
NOTE: An approval of falsework plans does not imply that OSHA regulations are satisfied, that the Iowa DOT, or the project engineer assumes any liability for the falsework.
Falsework Inspection
Contract requirements governing falsework construction are contained in
Specification 2403.17 under
"Design and Construction of Forms and Falsework."
The project engineer is responsible to inspect the falsework as it is erected to ensure that construction:
Note: Any inspection and/or acceptance by the project engineer is not intended to relieve a contractor of responsibility under the contract for falsework design and construction.
By specification, a contractor is responsible for proper evaluation of the quality of their falsework materials. However, the project engineer should not permit use of any material, when there is doubt as to the materials ability to safely carry the load. If there is any question, the contractor should be required to perform a load test or furnish other evidence of structural adequacy.
Timely inspection is essential. Falsework deficiencies should be brought to the contractor's attention at once. Deficiencies include:
If the contractor fails to take corrective action, a non-compliance notice shall be issued. Corrective action will be required prior to placement of any additional dead or live load to the support structure.
Falsework Foundations
Specifications require that falsework piling be driven to adequate bearing unless mudsills
or spread footings can be founded on rock, shale, compact gravel, coarse sand, firm clays
in natural beds, or well-compacted fill.
A. Falsework Piles
The pile bearing value required to support the design load must be shown on falsework drawings, and the pile driving operation must be inspected sufficiently to ensure that falsework piles attain required bearing.
B. Mudsills and Spread Footings
Foundation material should be inspected before the footings are placed.
To ensure uniform soil bearing, falsework pads must be set on material that provides a firm even surface, free of humps or depressions within the pad bearing area. If necessary to obtain uniform bearing, a thin layer of sand may be used to fill in surface irregularities.
Continuous pads must be analyzed differently than individual pads, and the two should not be considered equivalent. A change from one to the other requires resubmittal for review by the Office of Bridges and Structures.
Falsework pads should be level. Benches in fill slopes should be cut into firm material, with the pad set well back from the edge of the bench.
Many soils lose their supporting capacity when saturated. Adequate falsework construction must provide for drainage and protect pads from being undermined or ponded in water.
C. Soil Load Test
Materials
One aspect of a falsework design and review is based on the use of undamaged, high-quality materials.
Material strength values must be reduced if lower quality materials are to be used. Obviously, evaluation
of the quality of materials actually furnished is an important, and essential, part of the falsework
inspection procedure.
A. Timber
Falsework materials delivered to the job site, should be equal to or greater than the grade, or type of material, assumed in the design review. Timber having large shakes, checks or knots, or which are warped or split, should not be used at critical locations. Abused timber, although stress graded, may no longer be capable of withstanding the original allowable stress.
Rough sawn timbers should be measured to determine their actual dimensions. Unlike surfaced/finished material, the dimensions of rough-cut timber are not uniform from piece to piece. The variation may be appreciable, particularly in the larger sizes commonly used for falsework posts and stringers. If actual dimensions are smaller than the dimension assumed in design, the member may not be capable of carrying the imposed load without overstress. Therefore, undersized material should not be incorporated into the falsework, unless the design is reevaluated using smaller dimensions.
B. Structural Steel
Welded splices should be inspected visually for obvious defects. Radiographic inspection or other methods of nondestructive testing will not be required as a means of determining the quality of the splices unless the project engineer has reason to believe the welds are defective.
If falsework design is based on using steel other than A36, the contractor should be required to furnish evidence that all beams furnished are in fact the grade of steel as noted on the falsework plans.
C. Manufactured Products
When manufactured assemblies are used in falsework, they shall be shown on the falsework plans along with their identification number. Actual assembly shall be clearly and permanently marked with the identification number.
Identification numbers will allow field inspectors to verify the capacity and proper application of various devices.
Identification by the contractor applies not only to jacks, beam hangers, overhang brackets, and similar devices, but to all vertical steel shoring systems as well.
Manufactured products such as tubular steel shoring and steel overhang brackets are particularly vulnerable to damage by continual reuse. Fabricated units in which individual members are bent, twisted, or broken will have a substantial reduction in load-carrying capacity. Steel shoring materials should be examined carefully prior to use. Shoring components should not be used if they are heavily rusted, bent, dented, or have broken weldments or other defects. Connections, in particular, should be examined for evidence of cracked or broken welds. Miscellaneous components such as screw jack extensions, clamps, and adjusting pins should be inspected as well.
Proprietary scaffolding must be used as intended and not subjected to additional stresses or conditions for which it was not originally designed and tested.
D. Cable Bracing
Prior to installation, cable should be inspected to verify that the type, size, and condition (new or used) are consistent with design assumptions. Used cable should be inspected for strength- reducing flaws. Use of obviously worn, frayed, kinked, or corroded cable should not be permitted.
Particular attention should be paid to cable clamp fasteners. Improperly installed clamps will reduce the safe working load by as much as 90%. Also, the omission of the thimble in a loop connection will reduce the safe working load by approximately 50 percent. After installation, clamps should be inspected periodically and tightened as necessary to ensure their effectiveness.
This author could never remember which way to install cable clamps. The following little phrase may be beneficial:
"It does no good to saddle a dead horse."
While the phrase may seem nonsensical, it defines how to install clamps since a cable clamp has two parts - the "U-Bolt" and the "Saddle." Also, a cable has two parts, the wrapped non-continuous end (dead end) and the continuous portion which supports the load (live side). Therefore, always put the cable clamp's "saddle" on the live side and the "U-bolt" over the "dead end."
Project Quality
High quality work, particularly in such details as wedges, fasteners, bracing, friction collars,
jack extensions, etc., is critical to the proper performance of falsework. Accordingly, construction
details should receive close attention from the project inspector.
A. Timber Construction
Size and spacing of falsework members must agree with details shown on the falsework drawings.
Diagonal bracing, including connections, must conform to details shown on the falsework drawings.
Diagonal bracing should be inspected after any falsework has been adjusted to grade. Connections must be securely fastened to ensure their effectiveness in resisting horizontal forces. Bolted connections may need retightening.
Timber posts may be wedged at either the top or bottom for grade adjustments, but not at both locations. Large posts may require two or more sets of wedges (side by side) to reduce compression stresses perpendicular to the grain.
Blocking and wedging should be kept to a minimum. It is poor workmanship to extend a short post by piling up blocks and wedges. This practice should not be permitted.
Particular attention should be given to falsework bents where grade adjustment is provided at the bottom of the posts. Differential grade adjustment of posts within a particular bent may induce undesirable stresses in the diagonal bracing.
Splicing of wood posts will not be allowed unless shown on approved falsework plans.
The ends of spliced posts must be cut square. Proper size splice plates, and proper size, pitch and edge distance of nails need to be used. The need for a post splice should have been anticipated by the contractor and the splice detail shown on falsework drawings. If this is not the case, the contractor must submit a detail for approval.
Posts must be plumb and centered over the falsework pad or corbel.
Abutting edges of soffit plywood should be set parallel to the joists and continuously supported on a common joist.
A sufficient number of telltales must be installed to accurately determine the amount of joint take-up and settlement. Telltales should be attached to the joists as close as possible to the supporting post or bent.
Full bearing must be obtained between all members in contact. Deficiencies in this respect may be improved by feather wedging. If the joint requires more than a single shim or wedge, extra care should be taken to ensure that full bearing is obtained.
B. Steel Shoring (Scaffolding)
Shoring components should be inspected prior to erection. Any component that is heavily rusted, bent, dented or rewelded, or which is otherwise defective, should be rejected. Fabricated units having individual members that are bent, twisted, broken, or where welded connections are cracked or show evidence of rewelding should be rejected.
A base plate, shore head, or screw jack extension device should be used at the top and bottom of all vertical components.
All base plates, shore heads, and extension devices must be in firm contact with the footing at the bottom and the cap or stringer at the top.
Shoring components should fit together evenly, without any gap between the upper end of one unit and the lower end of the other unit. Any component which cannot be brought into proper contact with the component it is intended to fit, should not be used.
Shore heads, extension devices, and similar components must be axially loaded. Eccentric loads are not permitted on any shoring component.
All locking devices on frames and braces must be in good working order, coupling pins must align the frame or panel legs, and pivoted cross-braces must have the center pivot in place.
Shoring should be plumb in both directions. Maximum deviation from true vertical should not exceed 3 mm per meter (1/8 inch per 3 feet).
Miscellaneous Items
This checklist covers items that may be used in either type of support system:
Falsework Adjacent to Traffic
This will be an unusual situation in Iowa. If it occurs, the Office of Construction should be
notified.
Field Changes
If supplemental calculations are necessary to verify compliance with contract requirements, the
change will be considered substantial. In this case, the proposed change must be submitted for
review and approval in the same manner as the original drawings.
The following are examples of changes considered substantial and must be shown on revised falsework drawings, regardless of other considerations:
Inspection During Concrete Placement
As concrete is being placed, the falsework should be inspected at frequent intervals. In particular,
look for the following indications of potential failure:
Removal of Falsework
Specifications and applicable special provisions, contain specific criteria which must be met
before falsework may be removed. Project engineers should review these sections prior to
falsework removal operations.
The project engineer should discuss falsework removal methods and procedures at the preconstruction and/or prepour meeting. The need to provide for employee and public safety is of particular concern.
In general, all elements of the falsework bracing system must remain in place for the specified time period or until concrete attains the specific strength. For continuous concrete slab bridges that are stage constructed, the falsework for all stages must remain in place until the last stage concrete as attained the specified strength. The reason is that the concrete slab deflection does not occur until the falsework is removed and this deflection must occur for the full width of the bridge deck at the same time. In the case of cast-in-place, post tensioned construction, falsework elements must not be removed until stressing is completed.
11.32 BRIDGES - STEEL BEAM
Prebolting Meeting
The objective of a prebolting meeting is to establish a clear understanding of the principles
and purpose of rotational capacity testing, bolting procedures, Turn-of-Nut process, inspection
process, and the communication needs of the contractor and inspector during installation.
A prebolting meeting shall be held prior to erecting structural steel. In addition to
construction residency staff and contractor, notifications of the scheduled dates for
prebolting meeting and rotational capacity testing should be provided to:
- Office of Bridges & Structures Engineer
- Structural Steel Materials Engineer
- Office of Construction Structural Engineer
- District Materials Engineer
- Structural Steel Fabrication Inspector
Each of these persons can be a valuable resource during the prebolting meeting and throughout the structural steel erection process in providing technical assistance.
Suggested agenda items for discussion at prebolting meeting:
Suppliers to Furnish: | Mill Test Reports Manufacturer’s Certified Test Reports Distributor Certified Test Report Lot Numbers RC-Lot Numbers Statement of Compliance |
Iowa DOT to Furnish: | Mechanical Test Reports (Bolts, Nuts, & Washers) |
Contractor to Perform & DOT to Witness in Field: |
RC-Testing “Snug-Tightening” Turn-of-Nut Procedure Bolt Tension Verification of Installations |
Erecting Steel Beams
When erecting steel beams, the beams shall be supported until at least 25% of the bolt holes
are filled with drift pins and another 25% of the holes filled with fitting-up bolts which are
“snug” tightened. This will apply to both sides of the splice. (Refer to
Specification 2408.37.)
Beam support shall consist of adequate falsework or other approved means as directed by the engineer. The process of splicing of beams on the ground prior to lifting and setting should not be permitted until contractor’s methods are reviewed and approved by the engineer. The following are some of the criteria to be considered if this method is proposed:
Specification 2408.38 requires that the structure shall be adjusted to correct grade and alignment before placing permanent bolts in field connections. Grade and alignment should be checked by the contractor and verified by the inspector as each girder unit is set. All adjustments are to be completed before initiating the final phase of bolt tightening.
High Strength Fasteners
Specification 2408.39, Paragraph E.2
Turn-of-Nut method shall be followed for tightening all high strength fasteners.
High Strength bolts and nuts, which have been torqued as outlined below, shall not be reused.
This includes both black and galvanized bolts and nuts.
A. Bolting
Installation Checklist
B. Rotational-Capacity
There are two separate Rotational-Capacity requirements:
Field testing procedures are given in Materials I.M. 453.06B, Appendix A (long bolts), and Appendix B (short bolts). Supplemental step-by-step pictures are provided in Appendix 11-12 for visual reference, and Appendix 11-13 has Rotational-Capacity worksheets to document these tests. Since the worksheets are not in the Office Supply system, please photocopy as needed.
Rotational Capacity testing using Metric units has not been developed as of the date of this revision. Product suppliers of high strength fasteners are currently supplying English unit fasteners that have been “soft converted” to Metric units. At present, it is not known if or when producers will develop standard diameters, lengths, and rotational values for Metric fasteners.
In the interim, Rotational Capacity testing for Metric unit projects will continue to be performed in English units representative of the “soft converted” fasteners being supplied by producers. For all Metric unit projects involving structural steel, contact the Office of Construction for additional guidance on Rotational Capacity testing. In Appendix 11-13 is an example worksheet for long bolts completed in conjunction with the photographs. The example is only in English units and assumes:
28.4 + 0.6 = 29.0 kips
It is more than the minimum tension and thus passes the first requirement.
0.25 x | 0.75" x 29 kips x 1,000 lbs/kip = 453 ft-lbs. |
12" |
Since the "Measured" torque is less than the "Maximum" permitted torque the fastener passes the second requirement.
The "Minimum Adjusted" tension is computed by multiplying the "Specified
Minimum" tension times 1.15. For a 3/4 inch bolt this is:
28.4 x 1.15 = 32.7 kips
Since the "Corrected" Skidmore tension is larger than the "Minimum Adjusted" tension, the fastener passes the third requirement.
Failure of any one of the above criteria is cause to reject that Rotational-Capacity lot.
C. Turn-of-Nut Method
NOTE: As previously discussed in the Installation Checklist, adjustments in the specified Turn-of-Nut rotation may be necessary based upon the results of the Rotational Capacity test of fastener assemblies. If an RC test shows that a specified amount of rotation (i.e. 1/3 turn) does not fully develop the required minimum installation tension, then designate the new rotation required to achieve it.
3/4" Diameter Bolts | 7/8" Diameter Bolts | |||
Bolt Length |
Rotation from “Snug Tight” |
Bolt Length |
Rotation from “Snug Tight” |
|
0 - 3" | 1/3 turn | 0 - 3.5" | 1/3 turn | |
>3" - 6" | 1/2 turn | >3.5" - 7" | 1/2 turn | |
>6" - 9" | 2/3 turn | >7" - 10.5" | 2/3 turn |
NOTE: All additional rotations have a ± tolerance. Refer to Specification 2408.39, Paragraph E 2.
1" Diameter Bolts | 1-1/8" Diameter Bolts | |||
Bolt Length |
Rotation from “Snug Tight” |
Bolt Length |
Rotation from “Snug Tight” |
|
0 - 4" | 1/3 turn | 0 - 4.5" | 1/3 turn | |
>4" - 8" | 1/2 turn | >4.5" - 9" | 1/2 turn | |
>8" - 12" | 2/3 turn | >9" - 13.5" | 2/3 turn |
NOTE: All additional rotations have a ± tolerance. Refer to Specification 2408.39, Paragraph E 2.
D. “Snug Tight”
After ALL bolts in the connection are “snug tight”:
Note: No other markings on the structural elements should be allowed. The contractor may use marks on the sockets of their tightening equipment, in addition to match-marking (bolt, nut, and base steel), to aid in visually determining the correct amount of rotation to be applied.
Inspectors should observe this operation at intervals to make certain the match-marking is done correctly, and that the opposite bolt head or nut does not turn during the tightening process. Inspectors also should check to see if proper rotation has been made considering tolerances given at the bottom of the nut rotation chart. Remember that on a 6-sided nut, there is 60o from one point to the next point on the nut.
E. Inspection Wrench Calibration
When each device is calibrated, a calibration sheet will be issued indicating the date the test was performed. Contractors must keep the calibration sheet with the tension measuring device.
Attentiveness needs to be exercised when using this Calibration Sheet. The inspector needs to check the sheet and compare the "Indicated Load on Gauge" column to those values listed in the "AVG" column under "Actual Load on Testing Machine." These are usually NOT the same.
For Example: Refer to sample (English units) Calibration Sheet provided in Appendix 11-15. The Indicated Load on Gauge for 30,000 lbs., has an Average Actual Load of 29,000 lbs. (Gauge is reading 1,000 lbs. low at 30,000 lbs.) When one goes to a GAUGE of 40,000 lbs., the actual Average is 38,800 lbs., or a difference of 1,200 lbs. While it may not "seem" like much difference, it amounts to 3%.
NOTE: Be sure to take any difference (INDICATED versus ACTUAL) into account when calibrating the Job Torque Wrench!
2. Torque Wrench Calibration - Long Bolt
NOTE: 3 - 5 threads must be exposed behind the nut. Check and add washers if required. For longer bolts, steel shim plates should be used.
a. Tension bolt to 100 percent of "Minimum Bolt Tension" listed for a particular bolt diameter. Tension is read directly from the tension measuring calibrated device as corrected by accounting for differences between INDICATED versus ACTUAL. (Refer to Specification 2408.39 E.1 for "Minimum Bolt Tension.")
b. Apply inspection torque wrench, rotate nut or bolt, and increase tension by an additional 5%. Remember, a dial type wrench must be set to zero before checking torque. Record the inspection wrench's "TORQUE" when 105% of the tension is achieved.
NOTE: The turned element must be moving to indicate the >correct torque.
EXAMPLE: (English units)
Assume:
1. 7/8" Diameter bolt
2. Skidmore Calibration (Appendix 11-15)
Minimum Bolt Tension
39,250 lbs-force (Specification 2408.39 E.1)
Skidmore Calibration (from Appendix 11-15)
Gauge Reading 40,000 lbs-force
Actual Ave. at 40,000 = 38,800 lbs-force
Calculations
The torque reading on Inspection Wrench at 42,470± lbs-force is recorded as xxx.xx foot-lbs.
c. Repeat this process for a total of three fasteners.
d. The inspector notes the torque for three fasteners, averages this torque, and that becomes the Job Inspection Torque Value until the wrench is recalibrated the next day, or another size or length of bolt is to be inspected.
Inspector shall record:
3. Torque Wrench Calibration - Short Bolt
NOTE: for short bolts that will not fit the calibration device (ie: Skidmore) the following procedure
should be used:
At least once a day, three bolts of the same grade, size, and condition as those used in the structure shall be used to calibrate the job inspection torque wrench.
b. Initially tension fastener to values in Table 1 of Appendix 11-13.2 to establish “snug tight” condition.
c. Match mark bolt tip, nut corner, washer/shims, and the base steel (mark shall be a straight line).
d. Set inspection torque wrench to zero. Turn nut to total rotation values in Table For Nut Rotation from “Snug Tight” Condition in Specification 2408.39.E.2 and record torque. NOTE: The turned element must be moving to indicate the correct torque.
e. Test a total of three fasteners and average the recorded inspection torque wrench values. This average job inspection torque wrench value is to be used for inspection monitor check of completed fasteners in each connection according to
Specification 2408.39.E.3.F. Turn-of-Nut Inspection
2. The contractor shall use a "calibrated" torque wrench for the inspection operation. Contractors can have their torque wrenches calibrated at the Central Materials Laboratory in Ames.
3. Ten percent of the bolts which have been tightened in the structure shall be tested with the inspection wrench the same day as installed. At least two bolts, selected at random, in each connection shall be tested. If no rotation (nut or bolt head) is noted by job inspecting torque wrench and the faying surfaces are in tight contact, the connection shall be accepted as properly tightened. If any nut or bolt head is turned, inspection shall be applied to all bolts in the connection, and all bolts whose nut or head is turned shall be tightened and reinspected.
Bolts tightened by the Turn-of-Nut method may reach tensions substantially above minimum torque values specified, but this shall not be cause for rejection.
Care should be taken, however, to not overstress the bolts. If most of the bolts exceed 20% of minimum bolt tension when snug tightened, the contractor's procedures should be reviewed to determine:
4. Bolts and nuts must always be inspected prior to installation. Items of major concern are:
All dirt, foreign material, and rust must be removed prior to use. Black bolts may require reoiling to remove rust, etc. If reoiling is required, excess oil must be removed prior to installation. When rust cannot be removed by oiling, the bolt or nut must be rejected. Bolts or nuts with nicks or burrs on threads must be rejected. Relubrication will necessitate rechecking fasteners in the lot for Rotational-Capacity.
5. Plan ahead before girder splices have been fully tightened. Make necessary adjustments prior to tightening the bolts in a connection. The best way to assure that beam lines are straight and true is to:
This will require coordination between survey and inspection crews and the contractor.
G. Galvanized Bolts
When using galvanized hardware, a lubricant approved by ASTM A563 shall be applied to the nuts. Galvanized nuts "typically" are delivered to the project pre-lubricated. Usually, pre-lubricated nuts are stained and have a distinguishing color. If a lubricant has been applied at the fabrication shop, a field reapplication is not necessary provided original lubrication has not been removed in some manner. For situations where fabrication shop lubricant is in question, field application of beeswax, stick wax, or some other dry lubrication shall be required. Rotational- Capacity requires the test to be conducted with fasteners in the same condition as they will be during installation.
A WORD OF CAUTION:
Lubrication is required to minimize galling during installation. Since nuts are lubricated
(both threads and faces), it is important that nuts be rotated during tightening.
Fasteners (bolts and nuts of any type) shall not be tightened, then removed, reinstalled, and retightened.
Painting
A. New Non-Weathering Structural Steel
B. New Weathering (ASTM A 588) Structural Steel
C. Field Painting
11.33 BRIDGES - CONCRETE BEAM
Standard Design Sheet 1037 will be added to the plans when deck panels are allowed. If deck panels are used, shop drawings will be required. (Refer to Specification 2425.)
The following are some guidelines which should be followed when using deck panels:
NOTE: Styrofoam and/or "bead-board" will not be an approved substitute for fiberboard.
Pretensioned Prestressed Concrete Beam (PPC Beam) Erection
The contractor shall submit a written plan for their proposed PPC beam erection
sequence including ensuring PPC beam stability during erection and management of traffic if
construction is under active traffic conditions. This submitted erection plan is to be
reviewed by the Engineer to identify any concerns that may need to be addressed prior to
initiating the actual PPC beam erection.
Diaphragms (Steel or Concrete)
Steel diaphragms, if allowed, are shown on the plans for prestress concrete beam structures.
Shop drawings are required for steel diaphragms showing details of beam layouts, location of
the diaphragms, and location of the mounting holes.
Contractor requests for substitution of steel diaphragms for concrete diaphragms on prestressed concrete beam bridges over traffic will not be approved. The reason they will not be allowed on overhead bridges is that steel diaphragms are not considered structurally adequate to sustain potential impact from an overheight vehicle.
Intermediate concrete diaphragm construction on overhead bridges that involve staged construction have long presented a constructability problem. The problem relates to the difficulty in placing the concrete for the intermediate diaphragms that are located along the longitudinal construction joint.
This problem was previously resolved by allowing the use of steel intermediate diaphragms between the beams immediately adjacent to each side of the longitudinal construction joint. The remaining intermediate diaphragms between beams were still required to be concrete:
Upon further review by the Office of Bridges & Structures, a determination has been made that intermediate diaphragms in the location of the longitudinal construction joint may not be necessary. On future plans for staged bridges, the plan notes will state whether the intermediate diaphragms are omitted between beams immediately adjacent to the longitudinal construction joint.
High strength bolts for steel diaphragms shall be tightened by Turn-of-Nut method. (Refer to Specification 2408.39 for information on proper bolt inspection and installation.) Inspection and field installation acceptance will be based on observing proper Turn-of-Nut procedures. (A tensioning device and inspection torque wrench is recommended, but will not be required.)
Concrete diaphragms are intended to be placed monolithically with the deck slab. However, there are instances where allowance has been given for specific diaphragms to be placed prior to slab placement. These are typically intermediate diaphragms which tie adjacent beams together near the midpoint of the beam. If the diaphragm is placed before the slab, it shall be struck off at an elevation above the bottom of the deck, but below the bottom mat of steel.
Concrete diaphragms located at the piers and abutments must be placed monolithically with the deck. This is to ensure that the beam ends remain free to move during deadload deflection of the beams to prevent cracking over the piers and abutments. Consult with the Office of Construction in situations where the contractor requests to place concrete diaphragms before a deck placement.