SECTION 9080 - CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

 

PART 1 - GENERAL

 

1.01����� SECTION INCLUDES

 

A.�� Concrete Steps

 

B.�� Handrails

 

C.�� Safety Rail

 

1.02����� DESCRIPTION OF WORK

 

A.�� Construction of concrete steps.

 

B.�� Furnishing and installation of handrails.

 

C.�� Furnishing and installation of safety rail.

 

1.03����� SUBMITTALS

 

Comply with Division 1 - General Provisions and Covenants, as well as the following:

 

A.�� Submit color samples and product literature for primer, paint, and powder coating to be used on handrails and safety rail.

 

B.�� Submit shop drawings for handrails and safety rail.

 

1.04����� SUBSTITUTIONS

 

Comply with Division 1 - General Provisions and Covenants.

 

1.05����� DELIVERY, STORAGE, AND HANDLING

 

Comply with Division 1 - General Provisions and Covenants.

 

1.06����� SCHEDULING AND CONFLICTS

 

Comply with Division 1 - General Provisions and Covenants.

 

1.07����� SPECIAL REQUIREMENTS

 

A.�� Provide 1 gallon of color matched exterior grade polyurethane paint for each color specified, for the Contracting Authority�s maintenance use.

 

B.�� Label each container with the manufacturer�s name, product number, and color number.

 

1.08����� MEASUREMENT AND PAYMENT

 

A.�� Concrete Steps:

 

1.�� Measurement:� Measurement will be the area of concrete steps in square feet for each type of concrete step.� The length will be the horizontal length between expansion joints, and the width will include curbs.

 

2.�� Payment:� Payment will be at the unit price per square foot of concrete steps.

 

3.�� Includes:� Unit price includes, but is not limited to, reinforcement, expansion joint material, and preparation of subgrade.

 

B.�� Handrail:

 

1.�� Measurement:� Measurement will be in linear feet for each type of handrail, measured along the top of the handrail from end of rail to end of rail.

 

2.�� Payment: �Payment will be at the unit price per linear foot for each type of handrail.

 

3.�� Includes: �Unit price includes, but is not limited to, posts, mounting hardware or concrete grout, and finishing (painted, galvanized, or powder coated).

 

C.�� Safety Rail:

 

1.�� Measurement:� Measurement will be in linear feet for safety rail, measured along the top of the safety rail from end post to end post.

 

2.�� Payment:� Payment will be at the unit price per linear foot of safety rail.

 

3.�� Includes:� Unit price includes, but is not limited to, posts, pickets, mounting hardware, epoxy grout, and finishing (painted, galvanized, or powder coated).

 

PART 2 - PRODUCTS

 

2.01����� STEPS

 

A.�� Concrete:Class C concrete complying with Section 6010, 2.02.

 

B.�� Reinforcing Steel:Comply with Iowa DOT Section 2404.

 

C.�� Expansion Joint:� Comply with Iowa DOT Section 4136.03, A.

 

D.�� Forms: �Comply with Iowa DOT Section 2403.

 

2.02����� HANDRAIL

 

1 1/4 to 2 inches in diameter; ensure post diameter matches handrail diameter.

 

A.�� Steel: �Welded or seamless black steel pipe and posts complying with ASTM A 53, Grade A or B.

 

B.�� Aluminum: �Aluminum-alloy extruded structural pipe complying with ASTM B 429, alloy 6061-T6 or 6063-T6, schedule 40 (if specified; for use with grouted connection only).

 

C.�� Bends: �Provide manufactured pipe bends and connections for handrail.� Do not field bend pipe.

 

2.03����� SAFETY RAIL

 

A.�� Rails and Posts: �Provide 2 1/2 inch by 2 1/2 inch tubular high strength steel with 1/4 inch minimum wall thickness.� Comply with ASTM A 500, Grade B.

 

B.�� Pickets: �Provide 1 inch by 1 inch tubular high strength steel with 1/8 inch minimum wall thickness.� Comply with ASTM A 500, Grade B.

 

2.04����� FINISH

 

A.�� Painted:Provide factory-mixed paint / primer.

 

1.�� Primer: �Provide single component, water-based rust and corrosion resistant primer specifically designed for use on steel surfaces.

 

2.�� Paint: �Provide water-based, abrasion-resistant paint specifically designed for use on steel surfaces.

 

B.�� Galvanized: �When specified in the contract documents, galvanize handrail and safety rail.

 

1.�� Provide zinc coating complying with ASTM A 123.

 

2.�� Hot-dip galvanize components after fabrication.

 

3.�� For hot-dip galvanized components that will be powder coated, utilize the dry-kettle (pre-fluxing) process.� Air cool galvanized components.� Do not quench in water or chromate.

 

C.�� Powder Coated:� Apply powder coat to steel, galvanized steel, or aluminum handrail and safety rail when specified in the contract documents.� Comply with the manufacturer�s recommendations for surface preparation, application of primer, and application of the powder coating, in addition to the following minimum requirements.

 

1.�� Surface Preparation:

a.�� Steel Substrate:

1)�� Remove oils and surface contamination by solvent cleaning.� Comply with the requirements of SSPC-SP 1.� Rinse thoroughly with hot water or water pressure and dry completely.

2)�� Remove loose rust, loose mill scale, and other foreign substances by hand or power tool cleaning.� Comply with SSPC-SP 2 or 3.

3)�� Remove all dirt, grease, rust scale, mill scale, paint, slag, and other foreign substances by blast cleaning.� Comply with SSPC-SP 6.

4)�� Remove all blast cleaning products by means of vacuuming or compressed air.

5)�� Chemically clean surface to remove residual contamination, apply conversion coating, and apply sealing agent to prepare the surface for powder coating.�

6)�� Begin powder coating as soon as possible after surface preparation to prevent the development of iron oxide on the surface of the steel.

b.�� Galvanized Steel Substrate:

1)�� Remove all tears, spikes, high spots, or other surface defects caused by the galvanizing process using hand or power tools.

2)�� Apply an alkaline solution, with a pH between 11 and 12, to remove traces of oil, grease, and dirt.

3)�� Remove residual zinc oxide by spraying surface with a mild acidic solution (pH of 3.5 to 4.5).

4)�� Apply conversion coating to the surface and apply sealing agent to prepare the surface for powder coating.

c.�� Aluminum Substrate:

1)�� Clean surface by power washing to remove contaminants.

2)�� Clean surface with an aqueous alkaline solution by immersion or scrubbing with a soft brush.� Do not scrub with a steel bristle brush.� Dry completely after cleaning.

3)�� Remove oils and surface contamination by solvent cleaning.� Comply with the requirements of SSPC-SP 1.

4)�� Remove light deposits of aluminum reaction by-products by hand or power tool cleaning.� Comply with SSPC-SP 2 or 3.

5)�� Remove aluminum oxide by sweep blasting or chemical treatment:

a)�� Sweep Blasting:

i)��� Utilize oil-free compressed air to prevent contamination of cleaned surface.

ii)��� Utilize blast media with a MOH hardness of 5 or less, or utilize organic media such as corn cobs or walnut shells.� Do not roughen surface.

iii)�� Powder coat surface within 60 minutes of sweep blasting to prevent re-formation of aluminum oxide.

b)�� Chemical Treatment: Comply with ASTM D 1730 for Type B treatment.

6)�� Chemically clean surface to remove residual contamination, apply conversion coating, and apply sealing agent to prepare the surface for powder coating.

 

2.�� Priming:� Apply as recommended by coating manufacturer for specific substrate to all surfaces, unless specifically not required by coating manufacturer.

 

3.�� Coating:

a.�� General:

1)�� Provide complete multi-coat systems formulated and recommended by the manufacturer for the application indicated.

2)�� Provide urethane, TGIC polyester, polyester wrinkle, or non-TGIC polyester based powder coatings as recommended by the powder coating manufacturer to provide long term exterior durability.

b.�� Application:

1)�� Apply coating to the thickness specified by the coating manufacturer.� Comply with coating manufacturer�s recommendations for application of powder coating.

2)�� Apply coating in uniform thickness coats without runs, drips, pinholes, brush marks, or variations in color, texture, or finish.� Finish edges, crevices, corners, and other changes in dimension with full coating thickness.

 

4.�� Curing:� Cure the powder coating at the temperature and for the time recommended by the powder coating manufacturer.

 

2.05����� ATTACHMENT

 

A.�� Bolted Connection:

 

1.�� Anchor plate: �1/4 inch thick, 5 inch by 8 inch steel anchor plate with a 46,000 psi yield strength.� Paint or galvanize anchor plate to match handrail or safety rail.

 

2.�� Bolts: �Provide 3/8 inch galvanized anchor bolts or threaded rod with length as required to provide a 3 inch embedment.� Comply with ASTM A 36.

 

3.�� Adhesive Anchoring Material:

a.�� Epoxy complying with ASTM C 881, Type IV.� Provide appropriate epoxy class based upon concrete temperature at time of installation.

b.�� Grout on approved products list in Iowa DOT Materials I.M. 491.11, Appendix C.

 

B.�� Grouted Connection:

 

1.�� Polymer Grout: �Comply with Iowa DOT Materials I.M. 491.11.

 

2.�� Non-shrink Grout:Comply with Iowa DOT Materials I.M. 491.13.

 

PART 3 - EXECUTION

 

3.01����� INSTALLATION OF STEPS

 

A.�� Prepare Subgrade:� In fill areas, construct and compact subgrade to 95% of maximum Standard Proctor Density.

 

B.�� Forming: �Comply with Iowa DOT Article 2403.03, B.

 

C.�� Concrete: �Comply with Section 6010, 3.02.� Deposit concrete for the full depth of the steps in one operation.

 

D.�� Reinforcing Steel:� Comply with Iowa DOT Section 2404.� Provide a minimum 2 inches of cover on all reinforcing steel.

 

3.02����� INSTALLATION OF RAIL

 

A.�� General:

 

1.�� Install rail continuously with no gaps or breaks along the length specified in the contract documents.

 

2.�� Use welded connections between rail components.� Grind connections to remove sharp or abrasive edges and to remove other irregularities.

 

B.�� Handrail: �Install the top rail between 34 inches and 38 inches above the nose of the step tread.� Maintain a consistent height above the step treads.� Install the bottom rail midway between the nose of the step and the top rail.

 

C.�� Safety Rail:

1.�� Rails: �Install the top rail a minimum of 42 inches above the finished grade.� Install the bottom rail a maximum of 4 inches above finished grade.

2.�� Pickets: �Locate pickets in the center of the top and bottom rails and space evenly between posts.� Provide a maximum clear opening between pickets of 4 inches.

 

D.�� Posts: �Install posts at a maximum spacing of 8 feet.� Attach handrail posts in one of following two ways.

 

1.�� Bolted Connection:

a.�� Weld anchor plate to the bottom of the handrail posts.

b.�� Layout location and drill four 7/16 inch holes for anchor bolts at each post attachment point.� Drill holes with a carbide drill bit; do not core drill anchor bolt holes.

c.�� Apply adhesive anchoring material according to manufacturer�s published recommendations and install threaded rod or anchor bolts.

 

2.�� Grouted Connection:

a.�� Form a 6 inch deep hole in the concrete curb 1 inch larger than the outside diameter of the post.� Alternatively, hole may be core drilled in hardened concrete.

b.�� After the concrete hardens, set handrail posts into holes and temporarily secure.

c.�� Fill the void between the post and holes with non-shrink or polymer grout.

 

3.03����� PAINTING

 

Do not paint hot dipped galvanized or aluminum handrail or safety rail.

 

A.�� Mix paint and/or primer to correct consistency in accordance with manufacturer's instructions before application.� Do not reduce, thin, or dilute coatings or add materials to paint unless such procedure is specifically described in manufacturer's product instructions.

 

B.�� Shop coat handrail, safety rail, posts, pickets, and anchor plates with primer following fabrication.

 

C.�� Apply two field coats of paint upon completion of installation.

 

END OF SECTION