Section 2533.� Mobilization

 

2533.01���� description.

 

A.��� Preparatory work and operations for all items under the contract, including, but not limited to those necessary for:

�         The movement of personnel, equipment, supplies, and incidentals to the project site,

�         The establishment of all offices, buildings, and other facilities necessary for work on the projects, and

�         All other work or operations which shall be performed or costs incurred prior to beginning work on the various items on the project site.

 

B.��� Mobilization may include bonding, permit, and demobilization costs.

 

C.��� Nothing herein is to be construed to limit or preclude partial payments otherwise provided for by the contract.

 

D.��� A contract item for Mobilization will not be included for maintenance aggregate, materials, granular surfacing, or for any other minor projects.

 

E.��� When the proposal includes a lump sum item for Mobilization, the bidder shall indicate the bid price in dollars, and this is the contract price for this item. When the proposal does not include a lump sum item for Mobilization, all costs incurred by the Contractor for Mobilization are incidental to other work.

 

2533.02���� MATERIALS.

None

 

2533.03���� construction.

None.

 

2533.04���� method of measurement.

None.

 

2533.05���� basis of payment.

Payment for Mobilization will be as follows:

 

A.��� Partial Payments.

Partial payments may be made as follows:

 

1.���� Partial payment of mobilization will be made for each project within 30 calendar days after receipt of a signed contract. This partial payment will be either 10% of the contract price for this item or 1% of the original project sum, whichever is less. If the partial payment for a project is less than $1000, the Engineer will delay this partial payment until 5% of the awarded project total is earned.

 

2.���� When 5% of the original project sum is earned, either 25% of the contract price for this item or 2.5% of the original project sum, whichever is less, will be paid.

 

3.���� When 10% of the original project sum is earned, either 50% of the contract price for this item or 5% of the original project sum, whichever is less, will be paid.

 

4.���� When 25% of the original project sum is earned, either 100% of the contract price for this item or 10% of the original project sum, whichever is less, will be paid.

 

B.��� Full Payment.

Upon completion of all work on the project required by the contract, full payment will be made for this contract item, including any amount not paid as a partial payment.