8.80 USE OF SPECIAL EQUIPMENT
Use of MTVs is restricted to closed construction work zones. Applicable permits must be obtained for moving the vehicles to and from the project on the open highway for compliance with Code of Iowa weight laws. Do not allow the contractor to operate this equipment on the open road.
There is currently one model of MTV approved for use in Iowa. The equipment and limitations are as follows:
BARBER-GREENE MTV-3500
This vehicle weighs 34 500 kg (76,600 pounds) empty with a maximum additional 31 500 kg
(35 tons) mix storage capacity. It has four axles with large flotation tires. The front two
axles have 17.5R x 25 flotation tires and rear two axles have 20.5R x 25 flotation tires. Tire
pressure is 345 - 450 kpa (50 - 65 psi) inflation.
An empty MTV-3500 can safely cross all bridges that are not load-restricted, subject to the following conditions:
A partially loaded MTV-3500 can safely cross all bridges that are not load-restricted, subject to the following conditions:
Other Material Transfer Vehicles
Due to the possibly excessive high axle loads and tire contact pressure, material transfer
vehicles other than the Barber Greene MTV-3500 must be approved by the Office of Design and
Office of Bridges and Structures prior to use on a particular project. Approval for use can
be requested through the Office of Construction.
Pavements
Conditions and restrictions for use of other MTVs on primary and interstate pavements
are similar to those for the MTV-3500 as described in the previous section. An analysis of
the existing pavement structural numbers by the Office of Design is required prior to MTV
approval. This analysis is requested by the contractor through the project engineer.
Bridges
An analysis by the Office of Bridges and Structures of each bridge to be crossed is
required if the vehicle exceeds the allowable weight formula for bridges. This evaluation
is based on the MTV in an unloaded condition and must be performed prior to crossing any
bridges. The analysis is also requested by the contractor through the project engineer.
Following are the procedures to be followed in regards to obtaining MTV approval:
The DOT intends to take a "permissive" approach in regards to allowing MTV use on the surface course of multiple lift HMA resurfacing projects. This wil provide increased potential for continuous MTV use in the area of the pavement where the MTV's improvements to mat quality are most beneficial. However, MTV hopper load may be limited, based on results of the pavement analysis.
MTV use in conjunction with HMA placement must be closely monitored, and discontinued if evidence of detrimental distresses in the base or underlying pavement result. Such distresses would typically show up as deformation or rutting of base in full depth paving, or cracking and joint movement in existing pavement during an overlay. The contractor is responsible for repairing any damage to existing pavement or base caused by MTV operation.
Mat Smoothness Machine
Several contractors have used Cedarapids CR MS-3
or MS-4 Mat Smoothness Machines on paving and
resurfacing projects. This is an HMA material receiving hopper and elevator that deposits
hot HMA into the paver hopper. Use of this equipment allows for a more consistent paver
operation by providing some surge capacity for paver, only on a much smaller scale than MTVs.
In some cases, it can also help re-mix material and minimize segregation.
It weighs approximately 8 500 kg (18,800 pounds) empty and has a hopper capacity of 1.7 cu m (2.22 cubic yards). Weight restrictions are not a concern with this piece of equipment.
Even with MTVs or the CR MS-3
Windrow Pick-Up Equipment
Many Iowa contractors are equipped to construct HMA resurfacing and paving projects using windrow
pick-up equipment. This process is allowed by specification.
With this process, hot HMA is deposited in a windrow onto the pavement surface using bottom dump trailers. A windrow pick-up elevator deposits the material into the paver hopper. Again, the primary advantages are contractor efficiency, uniform speed of operation, and elimination of delivery trucks bumping into the paver.
Segregation has occurred on several projects on which this equipment was used. Truckload and longitudinal strip type segregation are potential problems. The contractor should balance their HMA delivery with the mat placement rate to keep the paver hopper at a nearly uniform level, which helps avoid segregation. Balancing delivery and placement also minimizes the need to either feed the hopper additional mix or remove excess windrow material with a mini-loader. The windrow should be placed to feed the center of the windrow pick-up machine. A windrow that is improperly located can place an eccentric force on the pick-up machine, which can force the paver to lose proper centerline alignment. It’s also important for the contractor to pick up all windrow material from the pavement surface, and not allow the windrow to extend more than two truckloads in front of the paver to avoid excessive cooling of the mix.
Normal HMA laydown temperature limitations apply to this process.
It’s has been shown that this process can be used successfully for the lower lift of a full
depth pavement; however, it
If streak type segregation is suspected, a trench can be sawed transversely across the lane and the profile viewed for voids and/or a non-uniform aggregate matrix. Cores can also be cut to ascertain if segregation is present. If segregation is determined to exist, costs of the coring or sawing will be at the contractor’s expense.
Normal HMA laydown temperature limitations apply to this process.