4.30 CONTRACTOR FURNISHED CONSTRUCTION SURVEY
According to specification Article 2526 "The Contractor shall furnish all survey necessary for construction of the project..." Additional survey work required because of plan revisions or changes directed by the Project Engineer shall be paid for as extra work according to Specification 1109.03, or be done by the Contracting Authority's survey crew.
Contractor's responsibilities include:
Contracting Authority will:
Special Attention Items
The Project Engineer should be notified and/or consulted for guidance if the
following conditions occur:
Documentation
Survey documentation shall be kept in a format acceptable to the Contracting Authority.
After project completion, survey documentation shall become the property of the Contracting
Authority.
Contract Administration
By specification, "Construction Survey" is identified as a "specialty
item."
"Construction Survey" is considered a professional service, therefore Davis-Bacon requirements do not apply.
If survey work is performed by someone other than the Contractor, a "Subcontract Request and Approval" form shall be submitted. All requirements of subcontractors are to be fulfilled with the exception of Davis-Bacon requirements.