3.70 IMPACTS TO ADJOINING PROPERTY
3.71 ACCESS LOCATIONS ON CONSTRUCTION PROJECTS
In brief, the access control policy, and its effect on construction projects, is the following:
Highways Where Access Rights Are
Acquired:
A location of access on highways where access rights have been acquired is termed, a
"Predetermined Access" (PDA).
The location of pre-determined accesses will be identified on the plans (typically, each plan & profile sheet will identify the PDA's on the sheet in the upper right hand corner), as well as recorded in the property deed. Because the location is included in the property deed, failure to construct the PDA at the designated location can result in future legal disputes and other difficulties. Therefore, it is imperative that PDA’s be constructed at the designated locations, with no adjustment made except with prior approval.
The station of the PDA location, as stated in the deed and noted on the plan, is the centerline of the entrance. PDA locations are defined as a point of stationing at the centerline of the highway with access locations generally authorized both left and right of this point. Construction of these accesses shall remain directly opposite and shall not be offset. The centerline of the PDA may be adjusted slightly. The adjustment shall not exceed ½ of the width of the entrance in order that the designated PDA location is located within the width of the entrance. For example, locating the entrance so that the PDA location "falls" on the foreslope of the entrance is not acceptable.
Adjustment of a PDA location greater than ½ of the width of the entrance that is necessary to be made during construction should be accomplished in accordance with the following procedure:
Highways Where Access Rights Are Not Acquired
Temporary Access for Contractor’s Use
Contractors requesting to construct a temporary access to a primary highway for their use,
such as a portable paving or crushing plant, shall submit a request for a temporary permit
for the entrance. The request should be submitted to the RCE, who in turn consults with the
District Engineer or their designee to obtain approval. The location must comply with
sight-distance requirements and relative location to existing entrances should be considered.
Refer to Policy No. 730.02.L. for additional information. Permits issued for temporary
access shall include a provision that requires the applicant to remove the access location and
restore the right of way to its original condition within a specified time frame (i.e. clean-up,
finish grading and seeding).
3.72 RELOCATION OF MAILBOXES
Mailboxes are property of the adjacent property owners and they are responsible for placement and maintenance of the mailbox and post.
Project Engineers are to provide written notification (minimum 30 days) to the affected mailbox owners to relocate their mailbox prior to construction. This notice can also be an opportunity to briefly describe the project concept and work schedule.
If a property owner fails to remove or relocate their mailbox and it is interfering with construction, the contractor should remove the mailbox and post and place near the ROW line.
3.73 INTERIM USE OF PROPERTY BETWEEN ACQUISITION AND CONSTRUCTION
If the parcel is needed for construction and removal of crops becomes necessary, the RCE should advise the property owner as soon as possible before the crops are destroyed. If a lease had been executed, the damages will be paid as described in the lease.
If a lease is not executed, the property owner should be advised in writing, by the Property Management Section, that the land is needed for construction and is not available for their use. The RCE should clearly stake the property lines as soon as a property owner is advised that the land is not available for their use. This is intended to ensure that the property owner does not inadvertently use ROW needed for construction.
3.74 INVOLVEMENT OF LAW ENFORCEMENT ON CONSTRUCTION PROJECTS
In cases where there are immediate potential risks to the safety of any person, an immediate call should be made to the law enforcement agency by whoever can make the call quickly. In these situations, it is not intended to require notification to the other offices prior to making the call.
In cases where the contractors’ equipment, property or personnel are being damaged, vandalized or threatened by the public, the contractor should involve law enforcement at their discretion. There is no intent to have the DOT intervene in those situations.