11.80 REINFORCED CONCRETE CULVERTS
11.81 DESIGN CHANGES ON CULVERTS
Article 1109.01B provides for exceptions/substitutions in the construction of reinforced concrete box culverts. As an option, a Contractor may construct a comparable size single or twin box culvert in English units using the RCB-G1-87 or TWRCB-G1-87 culvert standards in lieu of the metric culvert standards specified on the letting plans. A list of comparable English culvert opening sizes is provided in the above Supplemental Specifications.
Exceptions/substitutions on special designs that are not covered by the RCB-G1-87 or TWRCB-G1-87 standards will not be allowed. Some examples of special design conditions that are not covered by the referenced standards are:
The above special design conditions do not have existing English culvert standards, therefore culverts with the above special designs will NOT be allowed to be substituted by English culvert standard designs listed in the Supplemental Specifications table.
For culverts other than those noted above, the project engineer needs to obtain concurrence from the District Construction Engineer for situations warranting significant change(s). Checking the suitability of design for these culverts is the responsibility of the project engineer.
11.82 INSTALLING REINFORCING STEEL, PLACING CONCRETE, AND FORM REMOVAL
Field welding of deformed reinforcing steel is not permitted without approval of the Construction or Bridge Engineer as stated in Materials I.M. 558, Field Welding Inspection Manual.
Placing Concrete
Placing Concrete in Walls and Top Slab. Specification
2415.04, Paragraph B states that culverts, sidewalls, and top of slab may be constructed as:
If the contractor chooses to use the hardened concrete method, keyways will have to be installed to anchor the cover slab.
Article 2403.08, Placing Concrete, specifies that a tremie shall be used whenever the distance through which concrete must be dropped vertically exceeds 6 feet (2 m), except a 3 foot (1 m) drop shall not be exceeded for bridge floors and culvert slabs. For reinforced concrete box culverts, a tremie will be required if the concrete for the culvert floor and slab can not be placed within the allowable 3 foot (1 m) drop. For culvert walls, it is not possible to use a tremie for concrete placement due to the concentration of reinforcing in the walls and the lack of physical space to insert a tremie. This has been field evaluated and the determination has been made that the culvert wall thickness is sufficiently narrow that it functions like a tremie by confining the concrete when it is placed. To ensure satisfactory concrete placement in culvert walls, the following concrete placement procedure must be adhered to:
Following the above described concrete placement procedure for culvert walls has shown no segregation or cold joint problems.
Removal of Wall Forms
On large culvert jobs, it is a distinct advantage for the contractor to remove wall forms before the
top slab has attained sufficient age to remove supporting forms. This will be permitted under the
following conditions:
The wing walls and exterior surfaces of the barrel may be cured by any method specified in Specification 2403.10.
Removal of Slab Forms
Supporting forms for box culvert slabs may be removed when concrete has attained an age of 3 days and a
modulus of rupture 24 MPa (350 psi) for spans up to and including 1.2 m (4 feet), 27.5 MPa (400 psi) for
spans up to and including 1.8 m (6 feet), and 31 MPa (450 psi) for spans exceeding 1.8 m (6 feet). When
strength is not determined, forms for box culverts 1.2 m (4 feet) or less in width may be removed after
the concrete has attained an age of 7 days, and forms for box culverts over 1.2 m (4 feet) in width may
be removed in 14 days.
11.83 BOX CULVERT CURTAIN WALLS
If material to be excavated is of such nature that neat lines for the curtain wall cannot be maintained, the project engineer may allow forming and placing the curtain wall to the bottom of the footing. Mud must be prevented from working up into the concrete. If necessary, the footing for the curtain wall should be treated as provided by Specification 2402.04. As an option, and with the approval of the project engineer, steel sheet piling may be used instead of a poured curtain wall. This optional method of curtain wall construction is intended to address site conditions in which it is not reasonably practical for the contractor to dewater and excavate. Sheet pile curtain walls are not a substitute for cast-in-place curtain walls when they can be accomplished.
Sheet Pile Curtain Wall
Criteria for approving a sheet pile curtain wall alternate to the cast-in-place concrete curtain wall is as follows:
Reinforcement Placement
For culverts with parallel wings, "f-1" bars should be cut 305 mm (12 inches) from the bend
and installed as shown on the plans. When the footing is placed, "f-1" bars must be installed
using a 16 x 750 mm (5/8 inch diameter x 30 inch) bar as a lap splice.
NOTE: If metric bars are specified, this would be a 750 mm long, Number 15 bar.
For flared wing culverts, "t" and "u" bars must be installed when placing the curtain wall. Top of the curtain wall should be keyed or roughened, and flushed clean when the footing concrete is placed.
11.84 BOX CULVERT BELL JOINTS
The plan details for bell joint construction require that the bell joint be placed integrally with the culvert floor. Numerous requests have been received from contractors to permit a horizontal construction joint in the bell joint at the bottom of culvert floor. These requests have been made to simplify the bell joint and culvert floor construction sequence. It has been recognized that this would simplify the construction sequence. The constructability of culvert bell joints was field reviewed by the Office of Bridges & Structures and Office of Construction with a determination that permitting a staging construction joint in the bell joint would ensure improved construction quality.
Future culvert designs with bell joints will detail a permissible staging construction joint for culvert bell joints and will also require a keyway and installation of a “water stop” in the construction joint. For requests from contractors on current culvert projects to use a construction joint in culvert bell joints, contact the Office of Construction for a copy of the construction details.