CHAPTER 11
STRUCTURES
11.00 INTRODUCTION
11.01 REMOVAL OF BRIDGES
Office of Location and Environment staff inspect existing bridges for the presence of asbestos. Asbestos is occasionally found in utility conduits (i.e. transite pipe) that are attached to bridges. A tracking report is available that identifies the status of inspections of upcoming bridge projects. The report is available at: W:\Highway\EnvServices\RegulatedMaterial\ PDF Files\BridgeInsp.pdf
For contracts let on or after December 19, 2006, contractors shall submit the “Notice of Demolition”, by mail, to the Iowa DNR at least 10 business days prior to start of the bridge demolition. The contractor shall also send a copy of the completed form to the project engineer. The Office of Contracts will provide a partially completed “Notice of Demolition” form to the contractor with the signed contract. An example of a partially completed “Notice of Demolition” form (Form No. 536101) is provided in Appendix 11-26.
For contracts let prior to December 19, 2006, the contractor shall notify the Project Engineer of the intended starting date for demolishing a bridge. This notification shall be made at least 25 calendar days prior to starting the removal. The Project Engineer will forward the starting date to Office of Location and Environment staff for submitting the “Notice of Demolition” form to the Iowa DNR.
See Construction Manual Chapter 10.61 for additional information on Demolition Notices.
11.02 GUIDANCE FOR HEAVY EQUIPMENT & MATERIALS ON BRIDGES
1. For bridges with weight restrictions: all vehicles and equipment exceeding the posted limit.
2. Cranes or other construction equipments that are self propelled or transported to the project site by other means and considered legal or permitted during transport if:
3. The use of heavy construction equipment on bridge decks with:
4. Storage greater than 300 lbs/square foot of construction material on the bridge over a 4 ft x 8 ft area closer than 15 feet between loads.
5. Storage greater than 60.0 lb/square foot of construction material on the bridge over an area greater than 4 ft x 8 ft.
Heavy Construction Equipment Submittal Information
Heavy construction equipment will not be allowed on the bridge during construction
unless prior written approval of the Engineer is obtained. Approval shall be
obtained by submitting a written request to the Engineer. This request shall
include the following:
1. A detailed plan adequately describing the equipment and how it is proposed to be used. This plan shall contain, as a minimum, the following information.
2. The necessary calculations to verify that no component of the bridge will be overstressed during the proposed use of the equipment on the bridge. The calculations shall be certified by a Professional Engineer licensed to practice engineering in the State of Iowa.
11.03 TEMPORARY STRUCTURES FOR THE PROTECTION OF THE PUBLIC
There are many situations where the means and methods used by the Contractor in the performance of work on a bridge involve the installation of some type of temporary structure that is not included in the original design or identified in the plans. These temporary structures can vary greatly and need oversight review prior to installation to ensure that what is proposed will perform for the application intended.
A specification revision to Article 1107.08 was submitted to the Specification Committee for review and approval for the October 2008 General Supplemental. This specification revision will require a written plan from the Contractor to be submitted to the Engineer for approval. The written plan is to include the design of the means and methods used to provide protection and information for all design assumptions used in the design.
In the interim, it is recommended that Contractors be required to submit a written plan and design for temporary structures proposed as a means and methods that is structurally acceptable and provides protection for the public.
11.05 PILE DRIVING CAP AND HAMMER INFORMATION
Verification involves the weighing of the hammer and cap components at a certified scale.
Hammer weight verification only applies to the ram weight for gravity hammers. Power hammer ram weights are provided in manufacturer’s hammer specifications and do not require field weighing for verification.
Cap weight verification is required for all driving caps used with gravity or power hammers driving systems. Verification of cap weight must include the following:
Cap weight to include cap, cap cushion, and striker plate.
Cap insert weight when the insert is removable from the cap. Inserts are used in the bottom of some caps to change the shape of the cap opening to fit over H-pile, pipe, concrete, or wood pile. When an insert is required with the cap, it must be weighed and reported separate from the cap weight.
In the case where hammers and caps require verification, the District Materials Office should be notified to assist in weighing, stamping, recording, and reporting to the Office of Construction for update to the Caps and Hammers list. A form for reporting, entitled Identification Record for Pile Hammer and Cap, is provided in Appendix 11-1A.
The procedure for reporting changes or updates for caps and hammers was established in May 1986 according to the following.
The sequence for stamped identification number includes the letter D followed by the appropriate District number and three-digit number.
Example: D6001
D = Designation for District
6 = Designation for the District number
001 = Designation for the sequential number stamped
If verification results in a change to the current Caps and Hammers listing, provide a report to the Office of Construction with a request for update to the listing. The information for the update should include the identification number, mass (weight), contractor, and the date the identification stamp was made.
Diesel hammers are identified by manufacturer and model and do not require a stamped identification. Caps for diesel hammers are interchangeable and do require the identification stamp for inclusion in the Caps and Hammers list.
All reference to the ENR (formula) method of driving pile has been removed from the text. Instructions for counties and cities are included in Appendix 11-22. Users of the ENR formula for pile driving take note: The information is no longer being supported, however, material tables for different types of piling have been provided.